Construction progress

Novotel Tsaghkadzor — 10 floors, 310 rooms. Follow the construction progress. Updated monthly.

Progress~70%
Q4 2024Done

Foundation

Pile field of 285 supports. Monolithic slab 4,200 m². Geodetic control.

Q1 2025Done

Frame, floors 1–3

Monolithic reinforced-concrete frame of the first three floors completed. Load tests passed.

Q2 2025Done

Frame, floors 4–7

Slab pouring. Elevator shafts installed. Utility routing in progress.

Q3 2025Done

Frame, floors 8–10

Load-bearing frame completed. Roof installation started.

Q4 2025Done

Facade

Ventilated facade, panoramic glazing. Insulation to Accor standards.

Q1–Q2 2026In progress

MEP systems

Heating, ventilation, air conditioning. Electrics. Low-voltage systems. ~50% done.

Q3–Q4 2026

Interior finishing

Rooms finished to the Accor design. Furniture, plumbing, décor.

Q1–Q2 2027

Landscaping

Grounds, parking, landscape. SPA area, pool. Restaurant.

Q3 2027

Handover

State acceptance. Keys handed to owners. Hotel opening.

Photos from the site

Construction progress 1
Construction progress 2
Construction progress 3
Construction progress 4
Construction progress 5
Construction progress 6
Construction progress 7