Construction progress
Novotel Tsaghkadzor — 10 floors, 310 rooms. Follow the construction progress. Updated monthly.
Progress~70%
Q4 2024Done
Foundation
Pile field of 285 supports. Monolithic slab 4,200 m². Geodetic control.
Q1 2025Done
Frame, floors 1–3
Monolithic reinforced-concrete frame of the first three floors completed. Load tests passed.
Q2 2025Done
Frame, floors 4–7
Slab pouring. Elevator shafts installed. Utility routing in progress.
Q3 2025Done
Frame, floors 8–10
Load-bearing frame completed. Roof installation started.
Q4 2025Done
Facade
Ventilated facade, panoramic glazing. Insulation to Accor standards.
Q1–Q2 2026In progress
MEP systems
Heating, ventilation, air conditioning. Electrics. Low-voltage systems. ~50% done.
Q3–Q4 2026
Interior finishing
Rooms finished to the Accor design. Furniture, plumbing, décor.
Q1–Q2 2027
Landscaping
Grounds, parking, landscape. SPA area, pool. Restaurant.
Q3 2027
Handover
State acceptance. Keys handed to owners. Hotel opening.